We are pleased to share some project updates from Tom Hartley Junior's Car Showroom in Hook Norton. A
milestone was hit towards the end of 2024 as the initial groundworks phase completed with the
foundations, substructure masonry, and planks all finished. The Showroom and Car Barn steel
frames were erected, with cladding systems applied to the roofs and walls.
The beginning of the New Year has seen the site team off to a busy start as the composite floor decks have
been poured, with internal and external masonry works following as areas of the roof cladding progress.
Shortly the works will begin a new phase as we welcome metal stud partitions and our mechanical and
electrical contractors, Darke & Taylor, onto site to commence their works.
More updates to follow as this project progresses!